A rent rise on a periodic contract in Wales is a notice on form RHW12, at least two months ahead, and after the first one no more than once a year. Which contracts it covers, a worked example with dates, the fixed term and converted contract rules, and what the contract-holder can do.

11 min read

Sample account, the Rent page, with Payouts and Rent ledger: Collect rent automatically by Direct Debit with Set up payouts, then the monthly rent roll of £8,970 from 11 active tenancies, 55% collected this month, overdue rent of £1,140 with 3 tenancies behind, and 3 or more months’ rent owed 0, none at the Ground 8 threshold
Sample account, the Rent page on 17 Oct 2026: 78% collected this month, £4,295 of £5,495 charged
Sample account with made-up details, 17 and 21 Oct 2026

See how LetCompliance collects rent

Raising the rent on a home in Wales takes one form and two dates. The form is RHW12. The first date is the day you give it, and the second, the day the new rent starts, must be at least two months later. After the first rise, the next can start no sooner than a year after the last one took effect.

The sums are small each month and large over a year. A rise from £850 to £895 is £45 a month, or £540 a year, and a notice that fails because it was on the wrong form, sent the wrong way or dated too soon loses that money month by month until a correct one runs its two months. This guide covers which contracts the rule applies to, the notice, a worked example, fixed term and converted contracts, and what the contract-holder can do. The law was read on legislation.gov.uk and GOV.WALES on 20 November 2026.

The rule for a periodic standard contract

Most private lets in Wales are periodic standard occupation contracts, running from one rental period to the next. For them, section 123 of the Renting Homes (Wales) Act 2016 sets the whole procedure:

The landlord may vary the rent payable under a periodic standard contract by giving the contract-holder a notice setting out a new rent to take effect on the date specified in the notice.

Three rules follow in the same section:

RuleWhat it meansSection 123
At least two monthsThe period between the day the notice is given and the date the new rent starts may not be less than two months(2)
The first noticeMay specify any date, subject to the two months(3)(a)
Every later noticeMust specify a date not less than one year after the last date on which a new rent took effect(3)(b)

Two things stand out for landlords who know other parts of the UK. The first rise does not have to wait a year from the start of the contract: section 123 lets the first notice name any date, as long as the two months are given. And section 123 sets the notice, not the amount: it says nothing about how much the new rent can be. The Welsh Government's own summary is short: a landlord gives "two months' notice of a rent variation, which may be issued annually".

The notice: form RHW12

The notice must be on the prescribed form. The Renting Homes (Prescribed Forms) (Wales) Regulations 2022 prescribe Form RHW12, "Notice of variation of rent", for a notice under section 123, and GOV.WALES publishes it on its forms for landlords page.

  • Use the form, or one substantially to the same effect. Regulation 3(2) says a form substantially to the same effect is valid. A notice that is not in the prescribed form has no effect (section 236(3)), so a letter in your own words is a risk.
  • Put it in writing and give it properly. Section 237 allows it by hand, left at or posted to the dwelling or the contract-holder's last known address, or by email only where the contract-holder has said they are willing to receive documents electronically.
  • Count the two months from the day it is given. A notice left at the dwelling counts as given when it was left. If you post it, allow for delivery, because the two months run from the day it is given, not the day you sent it.
  • Keep a copy and the date. The date it was given decides when the next rise can start, a year after this one takes effect.

LetCompliance does not build RHW12, and England's rent increase form is not valid for a home in Wales.

A worked example with dates

A periodic standard contract with an occupation date of 1 May, rent £850 a month due on the 1st, and no rise since it began.

StepDateWhy it works
RHW12 given by hand, new rent £89520 JuneThe first notice may name any date
New rent starts1 SeptemberMore than two months after 20 June, and on the rent day
Earliest start for the next rise1 September the following yearNot less than one year after the last new rent took effect
Last day to give that next notice1 July the following yearTwo months before 1 September; give it in June to leave room for delivery

What a failed notice costs. Suppose the June notice went by email to a contract-holder who had never agreed to receive documents that way. It may have no effect, and the rent stays at £850. A fresh notice given on 1 August can name 1 October at the earliest. That is one month of the rise lost, £45, and the whole yearly cycle moves a month later with it. A notice that names too early a date has the same problem: give a fresh one rather than rely on it.

Aligning the new rent with the rent day, as the example does, keeps the arithmetic simple. Section 123 does not require it.

Fixed term contracts

Section 123 is a term of periodic standard contracts only, and RHW12 is the form for that notice. A fixed term standard contract follows section 134 instead: it "may not be varied except" by agreement between you and the contract-holder, or by or as a result of an enactment.

So during a fixed term, read your written statement first, and treat any rise as something to agree in writing. Once the contract is periodic, section 123 and RHW12 apply.

Contracts that converted on 1 December 2022

Tenancies that existed before 1 December 2022 became occupation contracts that day, and Schedule 12 to the Act adjusts the rent rules for some of them:

The converted contractWhat changesSource
Any converted contract that section 123 coversRent changes made before 1 December 2022 count as earlier variations, so the one-year rule runs from the last of themSchedule 12, paragraph 15(1)
One that, immediately before 1 December 2022, was a tenancy or licence to which section 13 of the Housing Act 1988 applied, or one of the other contracts paragraph 15(3) namesThe contract-holder may apply to a rent assessment committee for a determination of the rent, within 2 months following receipt of the noticeSchedule 12, paragraph 15(2) and (3); Renting Homes (Rent Determination) (Converted Contracts) (Wales) Regulations 2022, regulation 3
One with a private landlord that was an assured (not shorthold) tenancy with its own term on rent variationSection 123 does not applySchedule 12, paragraph 13B

If a contract-holder on a converted contract applies, the committee sets the rent on the assumptions the regulations lay down, and that rent becomes the rent under the contract unless you and the contract-holder agree otherwise. Keep the old tenancy agreement with the converted contract: it is the document that shows which row applies.

What the contract-holder can do

  • Pay the new rent from the date in the notice. Left unpaid, the difference is owed like any other rent.
  • Apply for a determination, if theirs is a converted contract in the second row above, within 2 months of receiving the notice.
  • End a periodic contract with their own notice, which must give at least four weeks (sections 168 and 169).

For a contract that began on or after 1 December 2022, section 123 contains no step for the contract-holder to have the new rent decided by anyone else. What protects them is the procedure itself: the prescribed form, the two months and the year between rises. That is also what protects you, because a notice that keeps to all three is hard to argue with.

A rise that lands well is usually one the contract-holder saw coming. A short note before the form arrives, with the new figure and the date, costs nothing.

Recording the new rent in LetCompliance

LetCompliance's notice and agreement builders are written for England. England's rent increase form, Form 4A, is refused for a property whose postcode is in Wales, and LetCompliance does not build RHW12. For a home in Wales, use the Welsh Government's form RHW12 and keep the signed copy, its dates and its reminders in LetCompliance:

  • The new rent and its start date go on the tenancy. For a home in Wales the tenancy form shows the Welsh rule in one line (at least two months' notice in the prescribed form, and a later rise not less than a year after the last) and does not ask England's questions. The new rent starts from the date you enter.
  • Rent is charged on its rent day at the right figure before and after, with paid, part-paid, late and missed recorded, a receipt for each payment and a rent statement that shows the change.
  • The RHW12 you gave is uploaded to the tenancy's documents. Where the contract-holder has agreed to email, send it from LetCompliance: each send goes into the activity log with its date and time.
  • Two reminders of your own on the dashboard calendar: the day the new rent starts, and two months before the earliest date for the next rise. Each is emailed to you that morning.
  • Direct Debit collects the new rent into your own Stripe account on the trial and paid plans. LetCompliance takes no commission; Stripe charges its own fee.

The help answer on homes in Wales lists what works for a Welsh postcode, and LetCompliance for landlords in Wales shows the whole set. For the rest of the Welsh file, see landlord software for Wales.

Put the new rent on the right date, and the next one in the diary. Single, for one property, is £7.99 a month.

Frequently asked questions

How often can a landlord increase rent in Wales?

On a periodic standard contract, the first notice can name any date as long as it gives at least two months; every later notice must name a date not less than one year after the last new rent took effect (Renting Homes (Wales) Act 2016, section 123).

What is form RHW12?

The Welsh Government’s prescribed form for a notice of variation of rent under section 123, set by the Renting Homes (Prescribed Forms) (Wales) Regulations 2022. A form substantially to the same effect is valid; a notice not in the prescribed form has no effect.

How much notice must a landlord give for a rent increase in Wales?

At least two months between the day the notice is given to the contract-holder and the date the new rent starts. If you post it, allow for delivery, because the two months run from the day it is given.

Can I increase the rent during a fixed term contract in Wales?

Section 134 says a fixed term standard contract may not be varied except by agreement between the landlord and the contract-holder, or by or as a result of an enactment. Section 123 and form RHW12 are for periodic standard contracts.

Can a contract-holder challenge a rent increase in Wales?

Where the contract converted on 1 December 2022 from a tenancy or licence that section 13 of the Housing Act 1988 applied to, the contract-holder may apply to a rent assessment committee within 2 months of receiving the notice. Section 123 itself contains no such step.

Sources and scope

All 15 sources

Every source above is a government or regulator’s page the guide cites, linked where it is used. This is guidance, not individual legal advice.

Ask an AI about this guide

Opens your assistant with this page as its source.

Share this guide

𝕏

You have read the guide. Now run the let.

Advertise and reference tenants, sign the agreement, collect the rent, log repairs and keep the tax figures ready all year. Certificates, deposits and deadlines are tracked alongside, so nothing expires unnoticed.

Plans from £7.99 a month, with a 3-day trial and no card. Making Tax Digital, recognised by HMRC, comes with every paid plan, not the trial.